Technical consultancy services for the retrofit of the Ispra site tri-generation plant

European Commission, Joint Research Centre (JRC), JRC.R โ€” Resources (Brussels), JRC.R.I.4 โ€” Maintenance and Utilities

The procurement aims to contract the services of preliminary design and assistance for the call for tender, the design and construction of the retrofit of the Ispra site tri-generation plant.
The Ispra site cogeneration plant (ISCP) was built during the years 2000โ€“2003 and put into operation in September 2004.
The 4 engines of the current ISCP are close to reaching the end of their life cycles. The plant is expected to operate effectively until 2020 upon accomplishment of a major maintenance programme to be completed by the end of 2017.
This is why a major retrofit of the plant is required.

Scadenza
Il termine per la ricezione delle offerte era 2017-09-22. L'appalto รจ stato pubblicato su 2017-07-26.

Chi?

Cosa?

Dove?

Storia dell'approvvigionamento
Data Documento
2017-07-26 Avviso di gara
2017-09-11 Avviso di aggiudicazione